Tenant improvement for a 9,400 sf office suite with knockdown texture and Level 4 finish throughout.
Scope
Challenge
GC needed drywall to release ceiling grid and MEP trim crews on a 15-working-day window. Demising walls ran to deck with fire-rated assemblies that had to pass inspection before closure.
Approach
Staged the work by zone so ceiling grid could start in the first zone while we were still hanging the last. Kept the fire-taping crew ahead of the inspector so nothing blocked close-up.
Keep reading
May 28, 2026
Houston's clay soil and humidity swings move houses, and drywall is where you see it first. How to tell a cosmetic crack from a structural warning, and why a proper repair is more than a tube of caulk.
May 20, 2026
Turning attic space into a bonus room is mostly a framing and mechanical job — but the drywall scope is where fire separation, permits, and the HOA's finish expectations all land. Here's what to plan for.
Share your plans or a walk-through and we'll come back with scope and a schedule.