How We Work
From start to finish
Every project follows a proven process. We handle layout, hanging, taping, and finishing with attention to detail at each stage. Our crew works efficiently while maintaining the quality standards our clients expect.

Layout
Measure, mark studs, plan cuts
1 day
Hang
Install boards, secure fasteners
2–3 days
Tape & Mud
Tape joints, apply compound
2–3 days
Finish
Sand smooth, final inspection
1–2 days
Most custom homes run 8–14 working days, start to finish.